Generate a Activities Summary Report for Day Plans in a Date Range
Get a day- and employee-wise summary of activities against the day plans in the selected date range.
- Log in to the web panel.
- Click REPORTS on the menu bar.
-
Scroll down to the Day Plan section.
- Click Multi Day Plan Summary/Detailed Progress Report.
-
Select one or more employees.
- Optional:
Ensure that Summary is selected for the level of detail.
It defaults to Summary.
-
Select Activities Based for Type.
Type defaults to Check-ins Based.
- Optional:
Change From and To dates.
Both From and To default to today.
- Optional:
Select HTML or XLS
for Load report as.
Load report as defaults to HTML.
-
Click LOAD.
The sample report shown below was based on the following test data:
- Both the selected employees have day plans, with two customers in each day plan.
- Vincent checked into F1 Networks and submitted an activity form.
- Vincent also checked into Trace Solutions who is not in the day plan, but did not submit any activity forms against it.
- Ramya did nothing.
Vincent's check-in into Trace Solutions on 2020-06-17 did not contribute to Actual Visits Without Day Plan, as it was just a check-in and he did not perform any activities.If you opted for HTML, the report opens in a new tab.
If you opted for XLS, the browser shows a dialog with Open With and Save File options.